시구이리 블록 3 및 오부아시의 4개 운영 지역: 서아프리카 광석 등급 프로필 2개, 침출 문제 2개

One mine replaces low-grade stockpile feed with 1.22 g/t ore; the other removes a single-decline bottleneck. Both change how reagents are consumed.

Gold leaching and adsorption reagents arranged for a mining chemical technical review

산업 뉴스 · 2026년 11월 5일

Two West African Grade Profiles, Two Leaching Problems

A feed-grade step change at Siguiri and a de-bottlenecking programme at Obuasi both reset the reagent control band — for different reasons.

빠른 답변

Within AngloGold Ashanti's 5 November 2026 brownfield programme, Siguiri in Guinea starts Block 3 at year-end with 1.22 g/t feed replacing low-grade stockpile material, at about US$70 million total capital for roughly 100,000 oz/y of additional output. Obuasi in Ghana, where blocks eight and ten currently share a single decline, plans to expand to four distinct operating areas by 2029 with a target of 400,000 oz/y. One change is a metallurgical step change in feed grade; the other is a throughput and access change. Both require the reagent control band to be re-validated, but the diagnostic path is different in each case.

주요 요점

  • Siguiri is a feed-grade event. Moving from low-grade stockpile to 1.22 g/t ore changes dissolution kinetics, reagent demand and the shape of the dosing curve.
  • Obuasi is an access and throughput event. Four operating areas by 2029 remove a single-decline bottleneck and change ore blend sequencing.
  • A nearby open pit is expected to contribute about 25,000 oz in 2027 and 50,000 oz around 2028, adding another distinct feed type.
  • 코트도르, the higher-grade area, is evaluated for access in the first half of 2029.
  • Never carry a control band across a feed change. Bottle roll or column testing on the new blend comes first.
  • 사양 일관성 across multiple operating areas reduces re-qualification work and makes batch deviations diagnosable.
날짜별 정보표 · 2026년 11월 5일 발표
사이트Disclosed detail
Siguiri, Guinea~US$70m total capital for ~100,000 oz/y additional output
Siguiri Block 3Starts at year-end with 1.22 g/t feed, replacing low-grade stockpile material
오부아시, 가나Blocks eight and ten currently share a single decline; four distinct operating areas by 2029
Nearby open pit~25,000 oz in 2027 and ~50,000 oz around 2028
Cote d'Or areaHigher-grade area evaluated for access in H1 2029
Obuasi target400,000 온스 / 년

Source: company expansion announcement, 5 November 2026. All figures above are disclosed project numbers; no reagent consumption figures have been estimated by the publisher.

1. Two mechanisms, one consequence

At Siguiri the variable that changes is the ore itself. A low-grade stockpile and a 1.22 g/t fresh feed do not have the same mineralogy, clay content, sulphide exposure or gold liberation. Dissolution rate, reagent demand per tonne and the shape of the leaching curve all move together. A dosing set-point tuned on the stockpile is simply not transferable.

At Obuasi the variable that changes is access and sequencing. Four operating areas feeding a shared circuit mean more blends, more frequent transitions and a wider range of residence times. A nearby open pit contributing 25,000 oz in 2027 and 50,000 oz around 2028 adds yet another feed. The reagent band must be robust across blends rather than optimised for one.

The consequence is the same: the control band must be re-established. The diagnostic path is not. At Siguiri, start with a new bottle roll curve. At Obuasi, start with a blend matrix and a transition protocol.

2. Four difficulties created by feed and access changes

2.1 Dissolution kinetics shift with mineralogy

Higher grade does not automatically mean proportional reagent demand. Sulphide, arsenic and clay content drive side reactions, so the new feed needs its own consumption baseline.

2.2 Blend transitions create invisible drift

When several operating areas feed one circuit, the blend can change without a formal campaign boundary. Operators then see consumption drift and compensate by over-dosing rather than re-testing.

2.3 Adsorption conditions change with solution chemistry

A different feed changes dissolved species in the leach solution. Carbon K/R performance should be re-checked in the new chemistry before throughput is increased.

2.4 Documentation across multiple areas

Multiple feeds and multiple delivery points multiply qualification work. One reagent specification, one test protocol and one COA/TDS/MSDS standard keep deviations traceable.

3. Tutorial: six steps to re-validate a control band after a feed change

  1. Define the new feed as a separate material. Record grade, mineralogy, clay fraction, sulphide and arsenic content, and particle size for Block 3 ore and for each Obuasi area and open-pit source.
  2. Run a bottle roll or column curve per feed at the intended pH band, sampling dissolved gold and residual reagent at 2, 6, 12 and 24 hours. Do not average feeds into one curve.
  3. Rebuild the dosing profile. Front-load where the new curve is steep and taper as it flattens; record the set-point per feed rather than per plant.
  4. Re-check the adsorption stage. Confirm AuCarb™ Gold Recovery Coconut Shell Activated Carbon (≥99% Hardness) still delivers the required K/R performance in the new solution chemistry.
  5. Write a transition protocol. Define what is logged and re-tested when the blend changes between operating areas, and who authorises a set-point change.
  6. Trace each campaign to its batch COA. Keep TDS and MSDS with the consumption log so any deviation can be tied to a specific delivery and a specific feed.

This sequence is deliberately ore-first. A feed change is a metallurgical event; treating it as a procurement event is why consumption drifts after expansions.

4. 문제 해결표

징후가능한 원인첫 번째 확인
Recovery lags after Block 3 startsDosing set-point carried over from stockpile oreNew bottle roll curve, pH profile
Consumption drifting without a campaign boundaryBlend transitions between operating areasBlend log, transition protocol
Carbon loading lower than design흡착 속도에 영향을 미치는 새로운 용액 화학R value retest, stage-by-stage tenor
Scaling on screens and emittersChanged water balance with new feedMake-up water hardness, 탄소ate trend
Batch deviations hard to diagnoseMultiple specs across areasSingle qualification, COA per lot

5. Three products, one specification

Dissolution is covered by AuCyan™ 시안화나트륨 NaCN (≥98.3%) at 18 MT MOQ; adsorption by AuCarb™ 금 회수용 코코넛 껍질 활성탄 (경도 99% 이상) at 15 MT MOQ, with AC50 attrition ≤1.5% and platelet ≤5.0% for stable screening; and the common-chemical alternative by AuLeach™ 금 침출제(GDA) – 무해함 at 28 MT MOQ, operating at pH 10.5–12. All ship factory-direct under FOB or CIF terms with batch COA, TDS and MSDS, packed for AuCarb™ in 25 kg heavy-duty laminated PE bags. Free laboratory test samples are available for AuCarb™ and AuLeach™.

6. 자주 묻는 질문

Q1. What changes at Siguiri Block 3?
It starts at year-end with 1.22 g/t feed, replacing low-grade stockpile material, within a plan of about US$70 million for roughly 100,000 oz/y of additional output.

Q2. What changes at Obuasi?
Blocks eight and ten currently share a single decline; the plan expands to four distinct operating areas by 2029 toward a 400,000 oz/y target.

Q3. What is the nearby open pit expected to contribute?
About 25,000 oz in 2027 and 50,000 oz around 2028.

Q4. When is Cote d'Or evaluated?
The higher-grade Cote d'Or area is evaluated for access in the first half of 2029.

Q5. Why does higher grade not solve the reagent problem?
Because sulphide, arsenic and clay content drive side reactions independently of gold grade. The new feed needs its own consumption baseline.

Q6. What is the first step after a feed change?
A bottle roll or column test curve on the new material, sampled over time rather than read at a single endpoint.

Q7. Why is Obuasi a different problem?
It is an access and sequencing change: multiple areas and a new open-pit feed mean frequent blend transitions rather than one metallurgical step change.

Q8. Should the carbon circuit be re-checked?
Yes. A different leach solution chemistry can change adsorption rate, so the K/R performance of AuCarb™ should be confirmed in the new conditions.

Q9. 어떤 인코텀즈가 적용되나요?
FOB 또는 CIF 조건이 적용됩니다.

Q10. AuCarb™는 어떻게 포장되나요?
In 25 kg heavy-duty laminated PE bags, with batch COA, TDS and MSDS per lot.

Q11. Can test samples support the re-validation?
Yes — AuCarb™ and AuLeach™ laboratory samples allow feed-specific testing before an FCL order is placed.

Q12. What is the date of the announcement?
2026년 11월 5일, 회사의 기존 부지 확장 프로그램의 일환으로.

7. 출처 및 내부 링크

AuCyan™ · AuCarb™ 가이드 · AC50 · AC55 · AC60 · BC1100 · AuLeach™ GDA · 골든 트라이앵글 · 3가지 제품 개요 · 화학 제품 FAQ · 업계 뉴스 · 문의하기

출처: 프로젝트 수치는 2026년 11월 5일자 회사 확장 발표 자료에서 발췌했습니다. 시약 사양은 다음과 같습니다. United Chemical 제품 데이터.

Re-validate a control band for your own feed change

문의하기 · WhatsApp +86 173 9270 5576 · info@unitedchemicalcn.com

  • 무작위 콘텐츠
  • 핫 콘텐츠
  • 인기 리뷰 콘텐츠

당신은 또한 같은 수 있습니다

온라인 메시지 상담

덧글 추가 :

+8617392705576왓츠앱 QR 코드QR 코드 스캔
상담을 원하시면 메시지를 남겨주세요
귀하의 메시지에 감사드립니다. 곧 연락드리겠습니다!
문의하기
온라인 고객 서비스