UNITED CHEMICAL · VALDKONNA UUDISED · 27. NOVEMBER 2026
A heap-leach ramp, then a CIL plant
Two processing routes on one site means two qualification programmes.
PT Merdeka Gold Resources Tbk (EMAS), majority-owned by PT Merdeka Copper Gold Tbk, recorded US$43 million in EBITDA as gold production surged 69% quarter on quarter, according to Macau Business reporting on the company's release. The Pani Gold Mine in Gorontalo, Indonesia, has mineral resources of 7.0 million ounces and an estimated 15-year mine life. Production is supported by a heap-leach facility with initial capacity of 8 million tonnes a year. The mine began mining in October 2025, achieved first gold in February 2026 and made its first sales in March 2026.
1. Stage one: heap leaching at 8 Mt/y
A heap-leach facility at this scale is a Süsinik-in-column operation in all but name. Gold dissolved in the pad is recovered from pregnant solution on carbon columns, where solution clarity and carbon loading rate dominate. BC1100 on hinne, mida tavaliselt hinnatakse veeru ja Kuhja leostumine service, selected on K and R values measured with the site's own solution.
2. Stage two: CIL from 2028
The company plans to develop a Leostussüsi (CIL) facility targeted to start in 2028 and scale to 12 million tonnes a year by 2029, with peak production of roughly 500,000–700,000 ounces a year by 2031. A CIL plant is a different reagent environment: carbon sits in agitated tanks, so ball-pan hardness and AARL attrition become as important as activity. The two stages therefore need two carbon specifications and two qualification dossiers, even if the same supplier serves both.
Kuldne kolmnurk – kolm toodet, üks tarnija
AuCyan™ naatriumtsüaniid NaCN (≥98.3%) · AuCarb™ kookospähkli koore aktiivsüsi (kõvadus ≥99%) · AuLeach™ kulla leostusaine (GDA) – mitteohtlik
3. Worked scale check
At 8 million tonnes a year through the heap leach, a tsüaniid demand of 0.15 kg/t implies about 1,200 tonnes a year of NaCN. At the planned 12 Mt/y CIL plant, demand at 0.25 kg/t would be about 3,000 tonnes a year. Even allowing for estimate error, the move from stage one to stage two multiplies reagent volumes by roughly two to three times. Qualifying the second-stage specification during stage one is the only sensible sequence.
Heap leach, 8 Mt/y at 0.15 kg/t: ≈ 1,200 t NaCN/year
CIL, 12 Mt/y at 0.25 kg/t: ≈ 3,000 t NaCN/year
4. Product fit across both stages
AuCyan™ naatriumtsüaniid NaCN (≥98.3%) supplies leaching at 18 MT konteineri kohta. AuCarb™ kuldse taastamise kookospähkli koorest aktiivsüsi (kõvadus ≥99%) is specified differently for column and agitated service at 15 MT konteineri kohta. AuLeach™ kulla leostusaine (GDA) – ohtlik is evaluated where permitted at 28 MT. All ship with batch COA, TDS ja MSDS in 25 kg vastupidavad lamineeritud PE-kotid all FOB / CIF tingimustel.
3b. Ramp-up is where carbon is lost
A 69% quarter-on-quarter production increase is good news with a hidden cost: ramp-up is the period when consumables are least controlled. Solution grades swing as new pad areas come online, irrigation rates are adjusted, and carbon is moved between columns to balance loading. Each change creates a window in which gold-bearing fines can leave the circuit or carbon can be loaded unevenly before elution. The mitigation is unglamorous but effective — log column inlet and outlet grades daily, sample carbon loading weekly, and keep a running mass balance rather than relying on monthly averages. When the 2028 CIL plant starts, the same discipline transfers directly, with the added variable of tank abrasion. Qualifying both grades during the current heap-leach phase is the only way to avoid a second learning curve in 2028.
3c. Ramp-up is where carbon is lost
A 69% quarter-on-quarter increase is good news with a hidden cost: ramp-up is the period when consumables are least controlled. Solution grades swing as new pad areas come online, irrigation rates are adjusted and carbon is moved between columns to balance loading. Each change creates a window in which gold-bearing fines can leave the circuit or carbon can load unevenly before elution. The mitigation is unglamorous but effective: log column inlet and outlet grades daily, sample carbon loading weekly and keep a running mass balance instead of relying on monthly averages. When the 2028 CIL plant starts, the same discipline transfers directly with the added variable of tank abrasion. Qualifying both grades during the current heap-leach phase is the only way to avoid a second learning curve.
5. KKK-d
Q1 — What did EMAS report?
US$43 million EBITDA with gold production up 69% quarter on quarter.
Q2 — What is Pani's resource?
7.0 million ounces of gold with an estimated 15-year mine life.
Q3 — What is planned for 2028?
A CIL facility scaling to 12 Mt/y by 2029.
Q4 — Does carbon spec change between stages?
Yes — column service favours activity; CIL favours hardness and low attrition.
Q5 — What terms are available?
FOB or CIF with batch COA, TDS and MSDS.
Q6 — Can carbon be tested first?
Yes — complimentary AuCarb™ and AuLeach™ samples for laboratory testing.
Qualify stage two during stage one
Send both flowsheets. We return a two-stage carbon and reagent specification with staged delivery terms.
Võta meiega ühendust · BC1100 · Kuldse kolmnurga ülevaade · Industry News
WhatsAppi +86 173 9270 5576 · info@unitedchemicalcn.com
Source: Macau Business, reporting on PT Merdeka Gold Resources Tbk (EMAS) results, November 2026.
- Juhuslik sisu
- Kuum sisu
- Kuum arvustuste sisu
- KESKKONNAJUHTIMISSÜSTEEMI SERTIFIKAAT
- Oksaalhape kaevandamiseks 99.6%
- Laiendatud AN lõhkeaine
- Metallnaatrium, ≥99.7%
- Naatriumvesiniksulfit 99% kvaliteetne tehase tarne
- 1Soodushinnaga naatriumtsüaniid (CAS: 143-33-9) kaevandamiseks – kõrge kvaliteet ja konkurentsivõimeline hind
- 2Naatriumtsüaniid 98.3% CAS 143-33-9 NaCN kulla sidumisaine, mis on oluline kaevanduskeemiatööstuses
- 3Hiina uued eeskirjad naatriumtsüaniidi ekspordi kohta ja juhised rahvusvahelistele ostjatele
- 4Naatriumtsüaniid (CAS: 143-33-9) Lõppkasutaja sertifikaat (hiina- ja ingliskeelne versioon)
- 5Rahvusvaheline tsüaniid (naatriumtsüaniid) halduskoodeks – kullakaevanduse aktsepteerimise standardid
- 6Hiina tehas 98% väävelhape
- 7Veevaba oksaalhape 99.6% tööstuslik kvaliteet
- 1Naatriumtsüaniid 98.3% CAS 143-33-9 NaCN kulla sidumisaine, mis on oluline kaevanduskeemiatööstuses
- 2Kõrge puhtusaste · Stabiilne jõudlus · Suurem saagis — naatriumtsüaniid tänapäevaseks kulla leostamiseks
- 3United ChemicalUurimisrühm demonstreerib autoriteeti andmepõhiste teadmiste kaudu
- 4AuCyan™ kõrgjõudlusega naatriumtsüaniid | 98.3% puhtusaste ülemaailmseks kullakaevandamiseks
- 5Digitaalne elektrooniline detonaator (viivitusaeg 0 ~ 16000 ms)
- 6Kõrge tugevusega ülitäpne põrutustoru detonaator
- 7tööstus elektridetonaator










Online sõnumite konsultatsioon
Lisa kommentaar: